The following proposed timeline is drawn from a document by construction firm Hensel Phelps, available at avl.mx/bj0.
Feb.-Oct. 2022: Parking lot improvements and airfield lighting.
Aug. 2022-Aug. 2023: Construct central energy plant.
March 2023-Aug. 2024: Add gates 6-12 to north concourse.
Sept. 2024-April 2024: Renovate north ticketing hall and air ticketing offices, renovate Level 2 administration space and expand south baggage claim.
July 2024-Dec. 2025: Expand south concourse
Sept. 2024-Aug. 2025: Renovate south air ticketing offices and expand north baggage claim.
Sept. 2024-Oct. 2025: Upgrade central security screening checkpoint and vertical circulation (ramps, stairs, elevators).
Feb-April 2026: Renovate temporary screening checkpoint.
Before you comment
The comments section is here to provide a platform for civil dialogue on the issues we face together as a local community. Xpress is committed to offering this platform for all voices, but when the tone of the discussion gets nasty or strays off topic, we believe many people choose not to participate. Xpress editors are determined to moderate comments to ensure a constructive interchange is maintained. All comments judged not to be in keeping with the spirit of civil discourse will be removed and repeat violators will be banned. See here for our terms of service. Thank you for being part of this effort to promote respectful discussion.