Woodfin greenway design seeks $958K in extra county funds

Buncombe County seal

Before the first fences are built and the first pavement is laid for the Woodfin Greenway, Buncombe County taxpayers will have to shell out nearly $958,000 more for design than the government had first estimated. The county Board of Commissioners will vote on the first $500,000 of that extra spending at its regular meeting on Tuesday, Jan. 21, in Room 326 at 200 College St.

According to a staff report available before the meeting by Josh O’Conner, the county’s director of recreation services, design of the project’s Riverside Drive segment had initially been estimated at $660,000. Buncombe was only responsible for $132,000 of that cost, with the remaining $528,000 covered by a Federal Highway Administration grant.

That projection, however, covers just 40% of the now-finalized price for laying out the greenway. “Due to the complexity of the Riverside Drive segment of greenway and cost escalation due to project engagement delays, the final design estimate has been received at $1,617,800,” O’Conner explains in the report.

Staff members, including County Manager Avril Pinder, recommend shifting $500,000 of county funds previously budgeted for the actual construction of the greenway to defray part of the extra design cost. The remaining $457,800 would be requested in the county’s budget for the 2020-21 fiscal year.

As O’Conner shared during a Dec. 17 pre-meeting of the board, the county’s greenway efforts have generally been challenged by regulatory issues and right of way acquisition, which have led to higher costs. Since adopting the 102-mile Greenway Master Plan in 2012, he said, the county has completed construction on less than half a mile.

In other business

Commissioners will also vote on accepting over $1.38 million in federal grant money from the Governor’s Crime Commission to expand the county’s Sobriety Treatment and Recovery Team program. The effort, run by Buncombe County Health & Human Services, aims to help parents with substance abuse issues and increase their ability to care for their children.

According to a staff report by Stoney Blevins, the county’s HHS director, the grant would double the START program’s capacity by funding four full-time staffers and additional contract work. Those positions would only be able to work through April 2021 without further grant funding or county budget allocation.

Under the “Good News” section of the agenda, Commissioner Joe Belcher plans to present the Order of the Long Leaf Pine Award to former Maj. Randy Smart of the Buncombe County Sheriff Department. Smart began as a deputy with the county in 1994 and retired in February 2019. In 2018, he was endorsed by then-Sheriff Van Duncan in the Democratic primary for Buncombe County Sheriff but lost to current Sheriff Quentin Miller.

Consent agenda

The board’s consent agenda for the meeting contains five items, which will be approved as a package unless singled out for separate discussion. Highlights include the following resolutions:

  • Dissolve the Energy Innovation Task Force and establish the Blue Horizons Community Council as its successor organization. The reorganized group will work to bring about “a clean energy future” for Western North Carolina.
  • Accept roughly $3,200 in drawstring comfort bags from the Arden Seventh-Day Adventist Church. The bags, which contain items such as stuffed animals, blankets, hygiene products and devotional books, are distributed to children entering the county’s foster care system.

The commission will hold a special meeting at 1 p.m. in the same location to interview candidates for the Parks, Greenways and Recreation Advisory Board. That meeting will be followed by a closed session on personnel matters, after which the board expects to take no action.

The regularly scheduled 3 p.m. pre-meeting of the board has been canceled. The full meeting agenda and supporting documents can be found at this link.

SHARE

Thanks for reading through to the end…

We share your inclination to get the whole story. For the past 25 years, Xpress has been committed to in-depth, balanced reporting about the greater Asheville area. We want everyone to have access to our stories. That’s a big part of why we've never charged for the paper or put up a paywall.

We’re pretty sure that you know journalism faces big challenges these days. Advertising no longer pays the whole cost. Media outlets around the country are asking their readers to chip in. Xpress needs help, too. We hope you’ll consider signing up to be a member of Xpress. For as little as $5 a month — the cost of a craft beer or kombucha — you can help keep local journalism strong. It only takes a moment.

About Daniel Walton
Daniel Walton is the former news editor of Mountain Xpress. His work has also appeared in Sierra, The Guardian, and Civil Eats, among other national and regional publications. Follow me @DanielWWalton

Before you comment

The comments section is here to provide a platform for civil dialogue on the issues we face together as a local community. Xpress is committed to offering this platform for all voices, but when the tone of the discussion gets nasty or strays off topic, we believe many people choose not to participate. Xpress editors are determined to moderate comments to ensure a constructive interchange is maintained. All comments judged not to be in keeping with the spirit of civil discourse will be removed and repeat violators will be banned. See here for our terms of service. Thank you for being part of this effort to promote respectful discussion.

2 thoughts on “Woodfin greenway design seeks $958K in extra county funds

  1. indy499

    Absurd estimate misses of that magnitude are only tolerated in government.

    There are only two interpretations:
    1. Gross incompetence
    2. Deliberate underestimates to obtain approval, knowing you just go back for more when the reality is uncovered.

    How about cancelling the 660k project which is now 1.6 million and probably rising?

Leave a Reply

To leave a reply you may Login with your Mountain Xpress account, connect socially or enter your name and e-mail. Your e-mail address will not be published. All fields are required.