We are on track with construction and are about 75% complete with the brewery building! We are still working on the Liquid Center (tasting room) and exterior spaces and still on track to be brewing by the end of 2015 and hosting you for a beer in Asheville in early 2016.

HAPPENING NOW:

Our mechanical and electrical is being finalized. Brewery IT is being installed, packaging and bottling piping is being completed and pipe work is being installed. Windows are going in. These installations will continue through August when we start commissioning the brewery. Commissioning is where we test every valve and pipe, lever and seal to make sure it works the way need it to and will take a couple months.

Structural steel is in place at the Liquid Center and radiant floors are in place. Next we’ll see walls go up and things will move quickly from there.

HAPPENING SOON:

Hardscaping – Anticipated neighborhood impact: 1 of 5

Soon you’ll start to see sidewalks, parking lots, curbs and other outdoor hardscaping replacing the dirt and thus decreasing dust in time for dry summer months.

Process Water Treatment Building Concrete- Anticipated neighborhood impact (3/5 noise and extended work hours)

On the north end of our site, near Hazel Mill and Emma Roads, you may have noticed a pole barn-esque building. This is our process water treatment facility.

Friday, July 3, 2015– Morning Concrete Pour– site active by about 3 a.m. and pouring starting around 4 a.m. and lasting about 10-12 hours. To have enough time to pour and set the amount of concrete needed, we have obtained City permits to start pouring concrete in the early morning. There will be generators and light towers, as well as back up beeping from the trucks.

CITY OF ASHEVILLE PROJECTS ON CRAVEN:

If you’ve been on or by Craven Street lately, you can see the great complete street, sidewalks and all, that is taking shape. Craven Street updates are available here. The French Broad River Greenway Westbank Greenway is coming along nicely as well. Penland Creek, which bisects our site and was named by the community in April 2015, is under going a major restoration and transformation (more on that soon as well!).

WORKING HOURS:

The standard work week is five days. While our target is to work Monday through Friday and frequent Saturdays, schedule delays will cause the work week to extend into Sunday on the rare occasion. Work will begin no earlier than 7 a.m. on weekday, as per City Noise Ordinance, and we extend it from 7 a.m. to 8 a.m. on Saturdays. Thank you for your patience in this process.

For more information and photos of New Belgium’s progress, click here.

SHARE
About Kat McReynolds
Kat studied entrepreneurship and music business at the University of Miami and earned her MBA at Appalachian State University. Follow me @katmAVL

Before you comment

The comments section is here to provide a platform for civil dialogue on the issues we face together as a local community. Xpress is committed to offering this platform for all voices, but when the tone of the discussion gets nasty or strays off topic, we believe many people choose not to participate. Xpress editors are determined to moderate comments to ensure a constructive interchange is maintained. All comments judged not to be in keeping with the spirit of civil discourse will be removed and repeat violators will be banned. See here for our terms of service. Thank you for being part of this effort to promote respectful discussion.

Leave a Reply

To leave a reply you may Login with your Mountain Xpress account, connect socially or enter your name and e-mail. Your e-mail address will not be published. All fields are required.