Road closures to occur during construction on two street bond projects

Press release from the City of Asheville: 

Short-term pain for long-term gain. Please keep that in mind during road closures coming up for two transportation bond projects.

In March, the City of Asheville shared information regarding a general construction schedule for the Kenilworth Road and State Street bond projects. (Find that announcement at this link.) Now we’re getting closer to where the rubber meets the road, so to speak.

To recap, both streets will undergo stormwater and sidewalk improvements prior to the actual road resurfacing. And that’s where we are in the process right now.

State Street

Pending weather, the City of Asheville Stormwater Division will close State Street from Allen Street to Montana Avenue daily from 8 a.m. to 5 p.m. April 27 to May 7. This will be to perform pipe replacement work in this area prior to the upcoming paving project. This will be a hard closure with residents and emergency personnel having access with minor delays. No thru traffic will be allowed. A detour will be set up during this construction.

Of note, the State Street project includes pedestrian improvements — flashing pedestrian beacons and new crosswalks — at Pennsylvania and Wellington streets. The Hanover intersection will have pedestrian signals incorporated into the traffic signals. These safety improvements were incorporated after checking in with the neighborhood.

The resurfacing is expected to occur in July.

The State Street project is also part of the City’s Phase 3 Bond package. The entire .8 mile  length of State Street will be resurfaced. The budget for this project is $1.28 million.

Kenilworth Road

Pending weather, the City of Asheville Stormwater Division will close Kenilworth Road from Chateau Place to Rosefield Drive daily from 8 a.m. to 5 p.m. April 27 through May 7. This will be to perform pipe installation work in this area prior to the upcoming paving project.  This will be a hard closure with no access during construction hours. No thru traffic will be allowed. There will be no detour for this closure.

This is being done in advance of the resurfacing, scheduled to begin around June 1 and expected to last four-five weeks. Milling to prepare for the resurfacing is expected to occur the last week of May.

The Kenilworth Road repaving project is part of the City’s Phase 3 Bond package. The entire 1 ½ mile  length of Kenilworth Road will be resurfaced. Existing speed humps will be reinstalled. The budget for this project is $800,000.

Thank you for your patience during this construction. Please reroute and avoid these areas, if possible.

The City’s bond transportation projects are on schedule and on budget. Keep up with progress by visiting Capital Project’s Bond Project Dashboard at this link.

https://dashboards.ashevillenc.gov/capital_projects

SHARE
About Thomas Calder
Thomas Calder received his MFA in Fiction from the University of Houston's Creative Writing Program. His writing has appeared in Gulf Coast, the Miracle Monocle, Juked and elsewhere. His debut novel, The Wind Under the Door, is now available.

Before you comment

The comments section is here to provide a platform for civil dialogue on the issues we face together as a local community. Xpress is committed to offering this platform for all voices, but when the tone of the discussion gets nasty or strays off topic, we believe many people choose not to participate. Xpress editors are determined to moderate comments to ensure a constructive interchange is maintained. All comments judged not to be in keeping with the spirit of civil discourse will be removed and repeat violators will be banned. See here for our terms of service. Thank you for being part of this effort to promote respectful discussion.

Leave a Reply

To leave a reply you may Login with your Mountain Xpress account, connect socially or enter your name and e-mail. Your e-mail address will not be published. All fields are required.