Debacle or sparkle?

You’d never know it from the kids splashing around the fountain or the young couples playing Frisbee on the lawn, but a decade ago, the 6.5 acres comprising downtown Asheville’s City/County Plaza was a mishmash of thoroughfares — three lanes of Patton Avenue traffic cut eastward past the Vance Monument, merging onto College Street — and ragtag green space featuring scraggly trees and a scarcity of benches.

Aug. 18 marked the fifth anniversary of Pack Square Park’s official public groundbreaking. But the relative calm of the space today belies its controversial history: years of delays, major cost overruns, closed streets, the continuing lack of public restrooms and a $2 million shortfall (see sidebar, “Payday?”).

Although informal plans for a park on the spot stretch back more than a century, the current incarnation roughly dates to 1999, when it was discovered that a water-line leak was undermining the street fronting the Biltmore Building. At the time, according to longtime downtown advocate Karen Tessier, the city had no plans (or money) to do much more than dig up the street, fix the problem and replace the dirt. “A number of us saw an opportunity to finally make George Pack’s dream a reality,” Tessier recalls. Instrumental in raising money for the new park, she considers it “the crown jewel” of Asheville’s decades-long downtown revitalization movement.

Not everyone is bullish, however. Asheville City Council member Cecil Bothwell has characterized the project as a “debacle,” with a final tab far exceeding the original estimates. “It was supposed to be done without government funds, but has consumed millions of tax dollars, and the [Pack Square] Conservancy owes the city $2 million it doesn't have,” he asserts, adding, “It’s a good example of a failed public/private partnership.”

The early years


Back in 1999, the Downtown Commission formed a task force to look at redesigning the entire area from Pack Square to City/County Plaza, seeking input from the public on what features they’d most like to see. Among the most-requested items were better landscaping with native plants, re-routing traffic, a better setting for events and performances, outdoor art and public restrooms.

The following year, the nonprofit Pack Square Conservancy was formed, charged with overseeing the park’s design and construction while raising money to build it and establish an endowment. The group has a volunteer board and two paid staffers.

For the first five years, the conservancy held public workshops, consulted architects and designers, drew up initial plans and worked on fundraising.

In 2005, Congress approved a $4 million earmark requested by Rep. Charles Taylor for transportation-related infrastructure costs (including digging up streets and re-routing Patton Avenue). And by the end of that year, the conservancy had raised $9.6 million to cover the actual park construction. In 2006, plans were drawn up for a large multipurpose pavilion/visitor center that would include public bathrooms.

Infrastructure projects continued well into 2007, but work was often halted till the N.C. Department of Transportation and the State Historic Preservation Office could review the progress. Outside entities — designers, archaeologists, structural consultants, mechanical engineers, utility company representatives, various city departments, property owners and county officials — had to be consulted every step of the way, and contractors, committees and the conservancy itself had to negotiate a labyrinth of approvals every time an unexpected problem arose.

“The public/private nature of the project guaranteed that it was no quick process. … It took one entire month just to remove some concrete buried under the road in front of the Jackson Building because of all the necessary approvals,” notes Gary Giniat, the conservancy’s executive director since early last year.

Along the way, the project was also beset by extreme weather delays and skyrocketing construction-material costs in the wake of Hurricane Katrina.

Rising costs, sinking timelines

In the meantime, the cost of the park continued to grow.

In 2000, the conservancy had estimated the cost of the park at somewhere between $500,000 and $2.5 million. By 2004, the plans had advanced in response to public input, and the estimated cost had jumped to $7.5 million, plus another $2.5 million for an endowment that would cover future maintenance and repairs. In September of that year, the Buncombe County commissioners signed off on a $10.5 million budget for the project (including a $2 million endowment), and early in 2005, they followed that up by agreeing to chip in $2 million in public moneys.
In 2007, the conservancy hired an independent firm to provide a revised cost estimate for the completed park, which came in at just over $20 million, not including the endowment. That figure has since been revised downward to reflect items scrapped from the plans; it now stands at about $18 million, not including the endowment.

At this writing, the conservancy has $200,000 in the bank, plus outstanding pledges totaling just over $700,000 and an additional $500,000 in as-yet-uncollected bequests. Meanwhile, the nonprofit owes the city roughly $2 million (see sidebar).

Intertwined with the cost increases was a series of missed deadlines. A 2001 agreement with the county set a firm completion date of Dec. 31, 2006. A June 25, 2007 press release stated, “The entire park [including the pavilion] is expected to be done by the end of 2008.” And an October 2008 audit by Buncombe County noted, “Completion is now slated for August 2009 … which is several years past its original completion date.”

Work on the park proceeded in stages, and it was finally wrapped up in March of this year.

For Bothwell, those delays remain highly problematic. “Having worked in the construction industry since 1970, the extended time frame of the park reconstruction was incomprehensible,” he maintains. “A for-profit company would never have permitted a major enterprise to drag on for five years, and the city could have accomplished the work in half the time and probably at half the cost.”

Bringing it to life

The infrastructure work was finished in August of 2007, when work on the park’s major features — the veterans memorial, the interactive fountain, the Bascom Lamar Lunsford Stage, Roger McGuire Green, the Reuter Terrace amphitheater and the massive bronze Pack Square fountain — began. By the end of 2009, local sculptor Hoss Haley (who designed the fountain) had also designed and installed the striking, stainless steel pergola that now crowns the stage.

Bothwell isn’t shy in critiquing the park’s features, either. “The completed park is replete with design and management failures — I think one might expect an experienced public-space architect to do better,” he comments. The placement of the stage, he maintains, hinders offloading of equipment, because Court Plaza is a fire lane and can't be blocked. “The popular Splasheville fountain is too close to the stage, so it has to be turned off during performances,” he said.

In addition, notes Bothwell, “The stage faces due west, forcing evening performers to face the setting sun. There is no permanent roof for the stage area. And the conservancy now tells us that the space which was once the center of Asheville's largest festival is not appropriate for large events.” Giniat, however, says it was never intended as a venue for major bands.

Local jazz singer Kat Williams, on the other hand, says, “Honey, for an outdoor venue, the stage is fabulous, because the sound really travels.” And theater designer Kyle Smith, who worked on the project, says the stage’s electrical components are better than those at Thomas Wolfe Auditorium. “You just don’t know they’re there,” he explains. “The architect went to great lengths to disguise them.”

Tiffs and trade-offs

Like most nonprofits, the conservancy took a hit after the national economy tanked in 2007. As early as 2008, the group discussed putting the pavilion — and its $2.5 million to $3 million price tag — on hold. Other features were also axed or postponed, including a custom-designed cover for the stage that would have cost another $250,000. For the time being, groups staging events can rent a temporary cover to prepare for bad weather.

As originally conceived, the pavilion would also have included offices for the conservancy, a large workshop/meeting space and a café (which drew the ire of neighboring restaurants). The nonprofit finally shelved those plans last year, citing financial concerns and a desire not to further postpone the park’s opening.

In March of 2009, the park received a $500,000 challenge grant from the Tourism Development Authority for the pavilion. Now, however, it may help fund a scaled-back informational kiosk that could further the TDA’s mission while addressing the need for restrooms. Hoping to minimize construction time and the impact on the park itself, says Giniat, the conservancy is hoping to start construction by late fall.

But key issues remain unresolved. “Public bathrooms are difficult to maintain and keep clean,” he notes. “Will they be heated? Will they be open in the winter or after dark? Will they have security or attendants? And who will pay for the maintenance? These are all questions that still need to be worked out.”

— Michael Muller can be reached at 251-1333, ext. 154, or at mmuller@mountainx.com.

SHARE

Thanks for reading through to the end…

We share your inclination to get the whole story. For the past 25 years, Xpress has been committed to in-depth, balanced reporting about the greater Asheville area. We want everyone to have access to our stories. That’s a big part of why we've never charged for the paper or put up a paywall.

We’re pretty sure that you know journalism faces big challenges these days. Advertising no longer pays the whole cost. Media outlets around the country are asking their readers to chip in. Xpress needs help, too. We hope you’ll consider signing up to be a member of Xpress. For as little as $5 a month — the cost of a craft beer or kombucha — you can help keep local journalism strong. It only takes a moment.

Before you comment

The comments section is here to provide a platform for civil dialogue on the issues we face together as a local community. Xpress is committed to offering this platform for all voices, but when the tone of the discussion gets nasty or strays off topic, we believe many people choose not to participate. Xpress editors are determined to moderate comments to ensure a constructive interchange is maintained. All comments judged not to be in keeping with the spirit of civil discourse will be removed and repeat violators will be banned. See here for our terms of service. Thank you for being part of this effort to promote respectful discussion.

15 thoughts on “Debacle or sparkle?

  1. Barry Summers

    Are you from Bahston? That’s the only place that ‘debacle’ rhymes with ‘sparkle’…

  2. Barry Summers

    I wonder how much time/expenses/lost fundraising can be traced to the two failed attempts to privatize this public space? The first was the Grove Park Inn’s attempt to take over the entire mid-section of the park, and the second was Stewart Coleman’s attempt to place condos in the lower section. Both debacles cost the Conservancy a lot of energy/consternation/trust in the community, etc.

  3. Barry Summers

    Not that I want to dredge all that up again, but I’m surprised that there isn’t even a glancing mention of these controversies as they might relate to the financial/timeline issue.

  4. fellow ashevillian

    I was just in London and marveled at the underground public toilets at Hyde Park. They are ceramic tile floor to ceiling and must be easy to clean (in that, in the middle of downtown London, they were in fact clean). A below-ground facility such as this would not eat into any of our public green space and would provide blessed relief to the citizenry. I’m sure the construction costs for a subterranean loo are far outside our already-exceeded budget, but that’s what I’d like to see…

  5. Media Watcher

    Your new photo format, where a click on the images, offers an enlargement and other images, is very nice.

  6. johann

    The entire deal is a let down. I haven’t been there since it has been finished. Compared to other smaller cities like Asheville I suppose it is a nice addition but for the amount of cash put into it I was expecting something much nicer.
    quote:
    she considers it “the crown jewel” of Asheville’s decades-long downtown revitalization movement.

    Crown jewel…far from it.

  7. LOKEL

    Something that I noticed yesterday when I was down in the park …. alot of the trees planted are in very tight quarters and close to the hard surfaces.

    This will no doubt lead to the buckling of the sidewalks/hardscape when these trees start to reach maturity in a few years.

    I would think that professional landscapers/arborists would have been consulted regarding the amount of space these saplings would need to mature to healthy trees.

  8. Brad Burleson

    While it was over-budget and does have its flaws, I think the park is a nice addition to downtown. My wife and I have spent several evenings down there watching the world go by, as well as taking family members visiting from out of town there. The visiting family members remarked on what a nice space it is. My young nieces had a lot of fun running around on the lawn near Splashville playing around while the rest of us enjoyed the evening, just sitting and talking. My wife and I often park on that side of town just so that we can stroll through the park on our way to eat/shop/etc. There are always people out enjoying the space and in the end, isn’t that what it’s was all about in the first place?

  9. Unit

    Unfortunate it took so long and cost so much, but in the end, it looks like a wonderful space.

    Naysayers notwithstanding. Bothwell’s design critique is laughable. I’m glad he didn’t design it – who knows what bizarre ideas he would’ve had…

  10. Hank Kennesaw

    I cursed the delays and inconvenience during the long construction. I must say that now that it is completed I do like it. I am disappointed though that the private money hasn’t come through in totality. I think a special ,tax should be levied on northern transplants who have agitated for changing Asheville into a place more like where they came from. Hopefully it will be enough to fill the private funds gap.

  11. Piffy!

    [b]I think a special ,tax should be levied on northern transplants who have agitated for changing Asheville into a place more like where they came from[/b]

    L.O.L.

Leave a Reply to Matt Mittan ×

To leave a reply you may Login with your Mountain Xpress account, connect socially or enter your name and e-mail. Your e-mail address will not be published. All fields are required.