North Fork Dam blasting schedule announced

Press release from the city of Asheville:

Construction began over the winter on the North Fork Dam Improvement Project and, as part of this project, there will be some blasting this spring, as previously announced.

We now have the initial blasting schedule and information useful to nearby residents.

·         The tentative date of the first blast has been set for March 26.

·         Blasting will be conducted between the hours of 9:30 a.m. and 3:30 p.m.

·         Typically there will be one to two blasts a day. These will be followed by one to three days of excavation.

·         A series of sirens will proceed and follow each blast. These typically will be a one-minute series of audible signals prior to the blast, followed by a prolonged signal after the inspection of the blast area.

We would like to remind nearby residents that this type of blasting (into the ground) differs from the type of blasting heard from the nearby quarry.

The blasting schedule is expected to last for two months.

About the project

The North Fork Reservoir and Water Treatment Plant serve as the City of Asheville’s primary drinking water source, providing 70% of Asheville’s water. With so many people, businesses and industries dependent upon this critical natural resource, special care and proactive measures need to be taken to ensure our water source and infrastructure are protected.

Planned modifications at North Fork Reservoir include:

·         Raising the dam by 4 feet;

·         Improvements to the principal spillway and the addition of an auxiliary spillway;

·         Modifications to the raw water piping through the dam and to the water treatment plant; and

·         Earth buttressing to reinforce the main dam and saddle dam for seismic stability.

The bid for construction services was awarded in October 2017 to the contractor Phillips & Jordan and construction began this winter.

Once completed, the dam will be able to better withstand inflow from severe storm events, as well as add capacity to the reservoir.

For more information about this important project, please visit the North Fork Dam Improvement Project webpage on the City of Asheville website. To navigate to the webpage, visit ashevillenc.gov, then type “North Fork Dam” into the search bar at the top of the page.

Questions? Email the project team at NorthForkDam@ashevillenc.gov. Or call Customer Service at 828-251-1122.

SHARE
About Community Bulletin
Mountain Xpress posts selected news and information of local interest as a public service for our readers. To submit press releases and other community material for possible publication, email news@mountainx.com.

Before you comment

The comments section is here to provide a platform for civil dialogue on the issues we face together as a local community. Xpress is committed to offering this platform for all voices, but when the tone of the discussion gets nasty or strays off topic, we believe many people choose not to participate. Xpress editors are determined to moderate comments to ensure a constructive interchange is maintained. All comments judged not to be in keeping with the spirit of civil discourse will be removed and repeat violators will be banned. See here for our terms of service. Thank you for being part of this effort to promote respectful discussion.

Leave a Reply

To leave a reply you may Login with your Mountain Xpress account, connect socially or enter your name and e-mail. Your e-mail address will not be published. All fields are required.